Defects Liability Period in Singapore: What It Covers and How to Use It
Your renovation does not end at handover. The defects liability period is your window to get problems fixed at the firm’s cost. Here is how to use it well.

Handover is not the end of a renovation. For the next year or so, you have a safety net called the defects liability period. Used well, it gets problems fixed at the contractor's cost. Used badly, or ignored, it quietly runs out. This guide explains what it is and how to use it in Singapore.
General information, not legal advice. Your own contract sets the actual terms.
What is a defects liability period in Singapore?
The defects liability period (DLP) is the agreed time after completion during which the contractor must rectify workmanship defects. In Singapore it is commonly 12 months, and some contracts allow longer. Check yours, because it should be stated clearly, along with when the clock starts.
What is a retention sum?
Many contracts hold back a retention sum, commonly around 5-10% of the contract value, until defects are fixed or the DLP ends. This gives the firm a financial reason to come back and repair problems. See where it fits in our guide to renovation contract clauses.
What is usually covered, and what is not
| Usually covered | Usually not covered |
|---|---|
| Peeling laminate and edge-banding | Normal wear and tear |
| Misaligned doors, drawers and hinges | Damage from misuse or accidents |
| Cracked or hollow tiles caused by workmanship | Items you installed yourself |
| Leaks from workmanship in wet areas | Products with their own manufacturer warranty (claim with the maker) |
| Paint defects and patching | Changes you requested after handover |
Equipment and fittings often carry separate manufacturer warranties, so keep the paperwork.
How to use the DLP step by step
- Do a thorough handover inspection first. Defects found before you sign are the firm's job to fix. Use the handover section of our renovation checklist.
- Keep a defects log. Date, location, photos and a short description.
- Report in writing, promptly. Email or message, quoting the contract clause. Do not rely on phone calls alone.
- Agree a fix date for each item, and note when it is done.
- Do a seasonal check. After heavy rain, look for seepage, damp patches and loose silicone around windows and wet areas.
- Do a final inspection a few weeks before the DLP ends and send a last list.
- Release the retention only when all items are rectified.
What if the contractor does not respond?
- Send a formal written reminder with a deadline, quoting the contract.
- If the firm is CaseTrust-accredited, you can raise the complaint with CASE, which offers mediation. See CaseTrust and HDB licences.
- For unresolved consumer disputes, the Small Claims Tribunals hear certain claims up to a monetary limit. Check the current limits and rules before you file.
- Keep everything: contract, variation orders, photos, messages and payments.
Why holding back payment matters
Once you have paid everything, your leverage is gone. Staged payments and a retention sum keep it. Choose a firm with a good record by comparing designers, and read how to choose an interior designer.
Frequently asked questions
How long is the defects liability period for a renovation in Singapore?
It is commonly 12 months from completion, though some contracts offer longer. Your contract should state the length and the start date.
What is the difference between a warranty and a defects liability period?
The DLP covers workmanship defects the contractor must fix. Warranties, for example on appliances or waterproofing, may be provided separately by the manufacturer or contractor, so keep both.
Should I withhold payment until defects are fixed?
A retention sum held back until defects are rectified is a common arrangement. Agree it in the contract before you start, instead of withholding payment unilaterally later.
defectsdlpretentionhandoverwarranty